Resumo de uma frase – Construction of a ground-mounted solar park in Finland’s Satakunta region is set to begin in the second half of 2024, with an estimated cost of €50 million ($53.1 million), aiming to generate 107 GWh/year and aligning with Finland’s national climate and energy strategy to increase reliance on renewable energy sources; meanwhile, AEE Solar is inaugurating a new distribution center in California to enhance operational capabilities and strengthen its nationwide distribution network in the solar industry.
Num relance
- Construction of a ground-mounted solar park in Finland to begin in the second half of 2024
- Estimated cost of the project is €50 million ($53.1 million)
- Solar park expected to be commissioned in early 2026
- Park will be located in the Satakunta region known for high radiation levels
- Solar park aims to generate 107 GWh/year
Os detalhes
Construction of a ground-mounted solar park in Finland is set to begin in the second half of 2024.
The project is estimated to cost €50 million ($53.1 million).
The solar park is expected to be commissioned in early 2026.
The park will be located in the Satakunta region, known for its high radiation levels.
The solar park aims to generate 107 GWh/year.
The municipality where the park will be situated already houses Finland’s nuclear power plant.
The municipality is eager to support renewable energy initiatives.
The solar park aligns with Finland’s national climate and energy strategy.
This strategy aims to phase out Russian fossil fuels and increase reliance on renewable energy sources.
The technology to be used for the solar park has not been determined yet.
Bifacial panels are being considered for the project.
The project is being led by Alight, a company that currently lacks power purchase agreements (PPAs).
Alight anticipates securing contracts with large corporate and industrial customers.
Alight plans to expand its presence in Finland.
The company aims to achieve a solar capacity of 500 MW to 1 GW within the next 12 months.
Other solar parks are being developed in Finland.
These include a 216 MW hybrid park in Alajärvi and Kyyjärvi, and a 500 MW power plant in Palloneva.
As of the end of 2022, Finland had 591 MW of installed PV capacity, according to the International Renewable Energy Agency (IRENA).
In a separate development, AEE Solar is inaugurating a new 140,000 sq ft distribution center in Visalia, California.
This facility will offer additional support to AEE’s clientele.
The new distribution center symbolizes the company’s growth and commitment to the solar energy industry.
The center aims to enhance operational capabilities, ensuring a higher level of service to customers.
The facility will have increased inventory capacity for solar modules, batteries, racking, and other components.
AEE Solar aims to strengthen its nationwide distribution network and supply chain through this expansion.
The expansion will result in shorter order processing timelines for customers.
A grand opening event was held on September 19th to commemorate this significant milestone.
These developments indicate Finland’s efforts to boost its renewable energy capacity.
They also show AEE Solar’s commitment to expanding its operations and improving customer service in the solar industry.
Artigo Raio X
Aqui estão todas as fontes usadas para criar este artigo:
A group of workers standing in a field, surrounded by solar panels and holding construction tools.
Esta seção vincula cada um dos fatos do artigo de volta à sua fonte original.
Se você tiver alguma suspeita de que informações falsas estão presentes no artigo, você pode usar esta seção para investigar de onde elas vieram.
pv-magazine.com |
---|
– Construction of a ground-mounted solar park in Finland is set to begin in the second half of 2024. – |
The project is expected to cost €50 million ($53.1 million) and will be commissioned in early 2026. – |
The solar park will generate 107 GWh/year and will be built in the Satakunta region, known for its high radiation levels. – |
The municipality where the solar park will be located is also home to Finland’s nuclear power and is keen to support renewable energy. |
– Finland aims to phase out Russian fossil fuels and increase its renewable energy sources as part of its national climate and energy strategy. – |
The technology to be used for the solar park has not been determined yet, but bifacial panels are a possibility. – |
The company behind the project, Alight, does not have any power purchase agreements (PPAs) in place but expects to secure contracts with large corporate and industrial customers. |
– Alight plans to expand its presence in Finland and aims to have 500 MW to 1 GW of solar capacity within the next 12 months. |
– Other solar parks under development in Finland include a 216 MW hybrid park in Alajärvi and Kyyjärvi, and a 500 MW power plant in Palloneva. |
– Finland had 591 MW of installed PV capacity at the end of 2022, according to the International Renewable Energy Agency (IRENA). |
solarpowerworldonline.com |
---|
– AEE Solar is opening a new 140,000 sq ft distribution center in Visalia, California – |
The new facility will provide additional support to AEE’s clientele – The distribution center symbolizes AEE’s growth and commitment to the solar energy industry – |
The facility will enhance operational capabilities and provide a higher level of service to customers – The new distribution center expands AEE’s inventory capacity for solar modules, batteries, racking, and other components – The goal is to strengthen the company’s nationwide distribution network and supply chain – |
The new facility will shorten order processing timelines for customers – AEE Solar hosted a grand opening event on September 19th to commemorate the milestone. |